2.7.2 Project 2
Project title: 
Construction of boardwalk 
Year/s when the project is active
2007/8 
Event/s within a year: 
1 event-October-March 
Zones or compartments
10
Expenditure
£38,000 staff time: reserve manager 6 days
Assistant reserve manager 8 days
Project priority
1
Justification for the project (i.e. the intended outcome):
The Countryside Council for Wales is in the process of improving public access at Cors Caron National Nature Reserve (NNR). As part of this programme of works it is necessary to construct a boardwalk which will provide access for the visiting public. The boardwalk will be suitable for wheelchairs and compliant with the Disabled Discrimination Act.
Potential impact on other features:
None
General background/bibliography:
See management plan.
Project methodology:
The work will be carried out by a contractor.
Specification of works
Section 1
Remove from site and dispose of approximately 65 m of existing boardwalk. 
Section 2
Construct 875 m of new boardwalk. 
Section 3
Design and construct a ramp to allow wheelchair access from the old railway line to the boardwalk at point X on enclosed map.
Boardwalk design
The boardwalk is to be 1.2 m wide between the kick boards. The kickboards should
be 75 mm high. The boardwalk must have a maximum gradient of 1:12. The maximum distance between passing places should be 150m. There should be no slope across the boardwalk.
The decking boards are to be transverse across the boardwalk and spaced a
maximum of 10mm apart. The decking boards are to be supported by two 100x 100mm stringers on the outside edges and a 100x50mm stringer down the centre. The decking is to be secured by two galvanised nails at each support point. The stringers are to be supported and fixed to two 100 x 50mm crossbeams fixed to
lOOx 100 mm posts by 16mm galvanised coach bolts. These supports should be
at least every 3 m. Each support post is to be dug or driven into the ground to a depth of 1,500mm where the boardwalk is raised less than 200mm above ground. Where the boardwalk is raised to a greater height than this the support posts should be dug or driven 2,000mm into the ground. The timber sections should be as follows:
Decking boards 150x40x 1,300mm
Crossbeams 100 x 50 x 1,500 mm
Stringers lOOx 100mm x variable length
Support post lOOx 100mm x variable length
Kick board 50x 75 mm x variable length
The tenderer should provide prices for constructing the boardwalk in
(a) Untreated sweet chestnut
(b) Pressure treated Douglas Fir
Both to be free of large knots and other defects.
Non-slip surfacing - Tenax Geogrid Type LBO 220 to be stapled to the boardwalk decking. CCW can provide details of one supplier of this material.
Storage and on site movement of materials
It is important to minimise the use of vehicles on site and avoid compacting or churning the surface. CCW will provide support to the contractor for transporting materials on site with a tracked ATV. Due to the presence of rare and sensitive species the locations for the temporary storage of new and redundant materials must be agreed with the CCW Warden.
Other requirements
The site is open to the public whist work is in progress. The contractor will be responsible for the provision of signs and barrier tape to warn the public and deter entry to work areas. The contractor must take all reasonable steps to ensure that materials stored on site are safe.
Note: The conditions of contract follow a similar pattern to those in the previous example.